So this is what AGRA Division Got this time in Rail Budget 2016.
List of the some works to be carried out :-
1. Mathura - Jhansi Third Line and Mathura - Palwal 4th Rail Line , Rs. 350 Crores
2. Yamuna Bridge - Agra Fort Double Line , New Railway Bridge On River Yamuna , Rs. 107.73 Crores ( I was personally...
more... Putting this suggestion from last 3 Yrs. Last time directly sent the proposal to GM. Happy about this work happening)
3. Idgah - Bharatpur - Bandikui Electrification , Rs 104 Crores.
4. 16 New Overbridge , 37 new subways b/w Agra-Mathura-Palwal , Rs. 1215 Crores
5. Dhaulpur-Sirmathura Gauge Conversion to BG and Extending line to Gangapur City(WCR).
6. Achnera ByPass to avoid LR of Trains going towards Mathura and Vice Versa.
7. PET Survey for a new line between Bharatpur-Deeg-Kama-Kosi 86 km
8. Reconnaissance Engineering cum Traffic Survey for a new line between Gwalior - Sahjahanpur via Fetehabad, Katana, Rajpur, Jalalabad (330 km)
9. Final Location Survey for doubling between Yamuna Bridge and Bandikui with Bridge on yamuna River
10. Railway Fly Over at Mathura Jn. Across Mathura - Agra main line (suggested time back)