As per my discussions with ETS Staff at Pune, it is understood that electrification (i.e. making 25 KV AC Traction 'live') will happen in phases over next 6 to 9 months. The start will happen from Puntamba (as PB-Manmad is already live AC). The work will come towards Daund and finally, in a single go, Pune-DD will be made live AC Traction! This can be accomplished easily in next 6 months. However, there are 2 major hurdles for the same, viz., land acquisition (small patch) required for TSS (near Yavat or Kedgaon) and NOC (or related legal formalities, etc).