#jbpnews
#JBPNIRNGCLOSUREUPDATES
#JBPNIRGNEWBGLINEUPDATES
1-work of dismantling old NG tracks with sleepers is started and around 80km route materials is dismantled till now out of 108kms and to stock dismantled materials is become very difficult as thief's are waiting to take the materials so for this SECR is now constructing a high iron sheet with barbwire fencing so that no theft can...
more... be done and as after the dismantling of materials of full 108kms till NIR there will be tonnes of materials which will be stored so SECR will auction all these materials in many stages and for this online n offline both tenders has been invited.
2-New BG rail route will decsrease the distance of many places from JBP/PNBE/HWH/CSTM and mainly distance of south bound stations will decrease more after the start of JBP-BTC-G new BG route in 1-2 yrs and JBP-Raipur/NGP travel time will also decrease and once this route will be started more n more south bound trains will start to use this route as a much faster route as this route will also be electrified along with new BG work then the travel time will also decrease along with less loco change and even JBP will become a main line for south bound trains sply along with NGP/BSP/Raipur trains