parts and parts of the section is electrified. upto maddur outer from SBC side its completely underwires.
MAD - poles and catenaries are present. wiring goin on.
HNK-same condition
MYA- POLES PLACED IN PITS. cementing and wiring required
between...
more... MYA and Y - parts are under wires parts are 'catenary' only
Y-poles are being erected
between KMS 104/1 AND 107 no signs. pits yet to be made
BYD- PITS YET TO BE MADE
BYD-PANP = most of it under wires
PANP, S, NHY- none
small patch between PANP TO S and NHY to MNGT poles are erected
substation work partially over near Y