the electrification works are going in two phases.
1-phase: Nallapadu to digavametta---- Almost poles and wiring got completed. After buliding substations it can go for energising
Target date: March 2016 Completed by June 2016
2-...
more... phase: Diguvametta to guntakal ---- Poles are erected from Guntakal outer to nandyal outer-- Target date for completing this section was
Febraury 2017
Hopefully By 2018 we may expect electric trains in this route