Charvattur to Mangalore Electrification Report as observed on 28/12/2016.
Wiring is almost 90-98% complete at Mangalore Central and Mangalore Junction,but they have to be joined and aligned properly.
I don't have images but saw an OHE van at Kumbla. Technician were aligning and doing some wire work at Uppala.
Train...
more... No.22610 reached 15-20 minutes late and I had to catch Ahmedabad Special at MAJN so rushed to Unreserved Ticket Counter to purchase MAJN ticket, so closely noticed the wiring work even at back and wires are there as well. Wires are there everywhere even at yards but they are not aligned and the work is underway and I have seen technicians working outside MAQ.I booked Sleeper class and I am upgraded to AC 3 TIER.