Two megablocks were taken near Nidi, one one 28/02 for subway work and other one on 03/03 for cut & connection. Even when I enquired on Twitter, CR GM replied me that work is progressing. One reporter has mentioned that March is the deadline for Nagothane Roha section. I don't konw whether they are working on Nidi Roha section or not. But it seems they will open Nagothane Nidi first.