Doubling updates of marwar jn- rani
at Somesar : bridge work and ground levelling work is going on with good pace. No sign of electrification.
Banta raghunathgarh : bridge work now started + ground work is going on
Auwa : ground leveling done now bridge work is goning on
in...
more... some patches track laying started btwn auwa - mj
pole erction for electrification started on newly commissioned sojat - chandawal route
also pole erection is going on sojat marwar but no pole on marwar jn station
doubling on khimel - moribera is mostly completed .still track laying is remaining near jawai band bridge
this stretch should get commisioned till october end