DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 97% done including cross bars at railway stations (Completion expected by Aug2019)
Brackets - 13% done (Completion expected by Oct2019)
Wiring - May start from 26 or 28-Aug from DAL/DaliGanj Junction (Completion expected by Dec2019)
SSP...
more... - Foundation at SD and STP completed (Completion expected by Dec2019)
OHE wire energized - Expected by end of Jan2020
CRS inspection - Expected by Feb2020
Commercial uses - Mar2020
** All provided dates are tentative.