News Entry# 81698  
Jul 07 2012 (3:44PM)  Airport Metro corridor to resume operations in 2 months: Government - The Times of India (timesofindia.indiatimes.com)
back to top
Major Accidents/DisruptionsDMRC/Delhi Metro  -  

News Entry# 81698     
   Tags   Past Edits
This is a new feature showing past edits to this News Post.

Posted by: Zindagi**  2621 news posts  
NEW DELHI: A day after deciding to suspend operations of the 16-month-old Delhi Airport Metro Express, government on Saturday claimed the high-speed corridor would resume services in two months time after necessary repairs, but left many questions unanswered.
Union urban development ministry, the Delhi government, Delhi Metro and Reliance Infrastructure were at odds to explain the decision to suspend operations for an indefinite period on the 23-km line owing to faults in civil structure on the corridor where trains are run at a speed of 105 kmph.
A committee comprising officials from the Indian Railways, Delhi Metro and Reliance Infrastructure is already going into the nature of defects and would submit a report within the next 10 days after which rectification works would be carried out.
...
Read more...
"The Reliance Infrastructure reported that there are some defects in the civil structure. There are problems with the bearing which is the interface between the pillar and girder. Repairs have to be done below the girders and it is in odd kind of locations," urban development secretary Sudhir Krishna told a press conference here.
Out of 2100 bearings on the elevated section of the corridor, nearly 230 of them need some correction or the other.
Krishna said Reliance Infra, the operator of the Line, insisted the operations should be suspended till the repairs works are done as it involves safety of passengers.
"By the end of August, we expect the Line to be functional again," he said in response to a volley of questions.
Sumit Banerjee, CEO, Infrastructure of Reliance Infra, admitted that the corridor was not making profits, but they would continue to run the Line and would not close it down.
"This decision is purely linked with safety," Banerjee said.
However, Krishna and Delhi chief secretary P K Tripathi were evasive on who will bear the cost of repairs works to be carried out. While Reliance Infra operates and maintains the corridor, the civil structure was built by Delhi Metro.