News Entry# 286829
  
Nov 26 2016 (08:37)  Lucknow Metro MD reviews operational preparedness for trials to begin from December 1 (timesofindia.indiatimes.com)
back to top
Commentary/Human InterestLMRC/Lucknow Metro  -  

News Entry# 286829     
   Tags   Past Edits
This is a new feature showing past edits to this News Post.

Posted by: rdb*^  130034 news posts
LUCKNOW: Lucknow Metro Rail Corporation (LMRC) Managing Director, Kumar Keshav visited the Transport Nagar metro station along with the Transport Nagar metro depot to review the operational preparedness with regard to the commissioning of metro train trial run from December 1, 2016.
At Transport Nagar metro station, Keshav inspected the platform, metro track, finishing, and electrical and mechanical (E&M) works being carried at the station. He asked the entire contractor to get them prepared in all respect with regard to commissioning of the trail run.
He also visited the Transport Nagar Metro depot
...
more...
where he inspected the operational preparedness related with flagging-off the trail run. He oversaw the track where the metro train would be placed at the time of flagging-off ceremony during the trail run and gave his feedback on improvements to be done.
Lucknow metro has already received the first set of 4 metro coaches to ply on the priority corridor of about 8.5 km from Transport Nagar to Charbagh from March 26, 2017 onwards. LMRC officials said total 6 trains would commute on this track daily from March 2017 at a gap of 2.5 minutes each. The priority section would have total eight metro stations.
While coaches have already reached the depot at Transport Nagar few days back, Lucknow metro team is currently testing the trial track, technical aspects and coaches' adaptability to various tests. Officials said that coaches are tested in many ways before launching them on trial tracks. It includes static testing (when coaches are standing on track), dynamic testing (when in motion) and oscillation trials.
After this the coaches are launched on test tracks. LMRC has made over 600 metre trial track inside depot where trials would begin December 1, 2016. After about a month, the coaches will be brought on to the real time corridor on Kanpur Road to move to and from one station to another. Public would get to board this metro from March, 2017 end.
Lucknow Metro is determining to commence the trial runs of the Metro train for the 8.5 km long priority corridor from Transport Nagar to Charbagh on 1st December, 2016 as per the stipulated deadline given by the Government.