Rail News
0 Followers
569 views
Other NewsSR/Southern  -  
Jun 25 2017 (16:48)   Trains gear up to chug off to Aryankavu from August

podhigai charal~   19 news posts
Entry# 2332708   News Entry# 306475         Tags   Past Edits
Preliminary works to lay railway track on three bridges at Kazhuthurutty were already commenced
Thenmala: With the direction of the Railway Board to complete the track laying works from Edamon to Aryankavu before June, trains are likely to chug off on the Aryankavu track from August. Deputy Chief Engineer Shankara Narayanan conducted inspection on the track.
According to sources, preliminary works to lay railway track on three bridges at Kazhuthurutty have begun. As part of the work, concrete sleepers and rails were brought to the worksite. The track laying work is pending at
...
more...
the tunnels and a few other parts. During the inspection, Deputy Chief Engineer had checked the progress of the work.
Earlier, the Railways had announced that new track would be ready by June. Since the work got delayed, N.K Premachandran MP met Railway Minister and sought immediate intervention to speed up the works.
If the works get over as per the new schedule, packing and trial run can be done in the first week of July and trains are likely to chug off from August.
At present, train service is in place from Edamon to Bhagavatipuram. After completion of track laying work between Aryankavu and Edamon, long distance trains from Kollam will run via Chenkotta. However, the drainage works are still pending.

  
3269 views
Jun 25 2017 (20:24)
12301HowrahRajdhaniTheGod~   2291 blog posts   1 correct pred (100% accurate)
Re# 2332708-1            Tags   Past Edits
An QLN se TSI 2 ghante mein jayenge log.
QLN TSI in 2 hrs by train

ARP (Advanced Reservation Period) Calculator

Reservations Open Today @ 8am for:
Trains with ARP 10 Dep on: Thu Dec 28
Trains with ARP 15 Dep on: Tue Jan 2
Trains with ARP 30 Dep on: Wed Jan 17
Trains with ARP 120 Dep on: Tue Apr 17

  
  
Scroll to Top
Scroll to Bottom


Go to Mobile site
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.