* The way BPL-Bina tripling is nearing completion, it can be expected that rest of the sections shall also be completed on priority like
NDLS-Palwal-4th line completed,
Palwal-MTJ (80 km)3rd line completed, 4th line construction started in 2016-17
MTJ-JHS (274 km) 3rd line -construction started in 2016-17
JHS-Bina...
more... (153 km) 3rd line -construction started in 2016-17
Bina-BPL-HBJ (143 km) 3rd line -in final stages of completion
HBJ-NGP- (384 km) 3rd line -construction already taken up in 2016-17,
NGP-WR (79 km)3rdL under construction (& 4th line shall be taken up in 2017-18),
WR-Kazipet-BZA (584 km)-3rdL construction taken up in 2015-16
BZA-Gudur (294 km)- 3rd line construction taken up in 2016-17
* DLI-MAS route is going thru transformation, as tripling has been taken up on almost full route, and a lot depends on the allocation to above projects in coming years.