ASH/Aishbagh - STP/Sitapur gauge conversion current update :
-
1. SCC/Sitapur Cantt. and STP/Sitapur Junction are not getting merged coz it was Speculated that SCC/Sitapur Cantt. and STP/Sitapur Junction might get merged while gauge conversion as both the station comes under NER and located parallel.
2. STP/Sitapur will have 3 PFs along with one through line
3....
more... SCC/Sitapur Cantt. already have 2 PFs along with with one through line where doubling with electrification is going on
4. SCC/Sitapur Cantt. and STP/Sitapur Junction are getting connected with two FOB (Foot Over Bridge)
5. STP/Sitapur Junction flooring work is on going
6. Train coming to SCC/Sitapur Cantt. from SPC/Sitapur City can come to STP/Sitapur Junction too as track been laid and waiting for interlocking and vice versa.
7. BUW/Burhwal - SCC/Sitapur Cantt. - ROZA/Roza junction doubling & electrification is on going which will connect STP/Sitapur Junction to GD/Gonda via BUW/Burhwal.
8. Train coming from ASH/Aishbagh can either go to SCC/Sitapur Cantt. or STP/Sitapur Junction too as track been laid and waiting for interlocking and vice versa.
9. Water hydrants are ready at STP/Sitapur Junction.
-
News courtesy Akash Aherwar (Member 868219)