Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Admin
 Bookmark
 Rating
 Correct
 Wrong
 Stamp
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
Forum Super Search
 ↓ 
×
HashTag:
Freq Contact:
Member:
Posting Date From:
Posting Date To:
Blog Category:
Train Type:
Train:
Station:
ONLY with Pic/Vid:
Sort by: Date:     Word Count:     Popularity:     
Public:    Pvt: Monitor:    RailFan Club:    

Search
  Go  
Full Site Search
  Full Site Search  
 
Mon Dec 10 03:59:35 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Gallery
News
FAQ
Trips
Login
Feedback
PostPost Trn TipPost Stn TipAdvanced Search

Blog Entry# 3193954
Posted: Mar 11 (16:07)

1 Responses
Last Response: Mar 11 (16:07)
  
Rail News
0 Followers
300 views
Other News
Mar 11 (15:38)   Acquire land after sanction of works: Railway panel

16591🔹Hampi Express🔹16592^~   3042 news posts
Entry# 3193954   News Entry# 331170         Tags   Past Edits
A railway panel has suggested that land for the national transporter's projects should be acquired only after sanction of works or before signing of construction contracts, to avoid delays in their completion.
According to a report of the statistics ministry submitted last month, more than three-fifths of the total 349 delayed central projects belong to the railways, causing a cost overrun of Rs 1.73 lakh crore.
"Delay in land acquisition and shifting of utilities are causing abnormal delay in commencing and completing the project. These two activities should be taken up and completed
...
more...
before finalising the contracts for actual execution of the work," the report said.
"These two should be taken up immediately after sanction of projects."
Under the present practice, construction contracts are processed without finalising drawing and plans, land acquisition and shifting of utilities like removal of trees, electrical poles etc., the report said.
The panel in its report on 'Improving Project Execution and Monitoring' has said while the completion periods are given as three to four years in the contract, in many cases it takes double the duration.
This, the panel said was adversely affecting the profit of contractors "leading to termination of many contracts and also arbitrations and litigations."
The report has said that General Managers should be delegated the powers for sanctioning part estimates and incurring expenditure for land acquisition and shifting of utilities to expedite the process.
The cost of the delay in railway projects can be estimated by the data provided in the statistics ministry report which monitored 350 projects of Indian Railways in October last year.
The total anticipated cost of the 213 delayed projects ballooned to Rs 2,96,496.70 crore from original cost of Rs 1,23,103.45 crore because of delays, it said, which is an overall cost escalation of 140.85 per cent.
The report of the rail panel was submitted to the Railway Board last month and is under consideration.

1 Public Posts - Sun Mar 11, 2018

ARP (Advanced Reservation Period) Calculator

Reservations Open Today @ 8am for:
Trains with ARP 10 Dep on: Thu Dec 20
Trains with ARP 15 Dep on: Tue Dec 25
Trains with ARP 30 Dep on: Wed Jan 9
Trains with ARP 120 Dep on: Tue Apr 9

  
  

Rail News

New Trains

Site Announcements

  • Entry# 4073462
    Dec 06 (12:50PM)


    There are some minor changes to the PNR Forum: 1. The main PNR feed will only show UN-predicted (by you) PNRs which are coming in. However, if there are replies, the PNR will show and will bubble to the top. Once you predict the PNR, it will go away from the main...
  • Entry# 4003283
    Nov 14 (11:24AM)


    This is an advance notice of a new feature that will be introduced within the next couple of days. The feature is called "Spottings". . 1. Any time you see a train ANYWHERE - while railfanning, while travelling in a train, while visiting a station, seeing someone off, receiving someone, while your train...
  • Entry# 3710716
    Aug 14 2018 (11:04AM)


    This is regarding the appointment of Monitors. For TLMs, we require a minimum of 1000 Confirmed TLs. For FMs, we require members to promise to abide by the guidelines and be free of controversies. For other Monitors, we require the member to be in good standing. . However, "eligibility" does NOT always mean...
  • Entry# 3645007
    Jul 20 2018 (03:28PM)


    This is an advance notice of an upcoming change: 1. We shall be removing the Login/Forum section from the RailCal app as it is cumbersome, buggy and lacking in features. . 2. We shall soon be introducing a dedicated app called "Rail Messenger" for both Android and iOS, for all blogging/messaging purposes. The app...
  • Entry# 3644431
    Jul 20 2018 (12:42PM)


    The following changes are being made: 1. To restore the fun back to PNR Predictions, PNR Predictions will NOT be hidden anymore. PNR Predictions by members can be seen by ALL, before and after Charting. New members often look towards our expert predictors for hints, and we are reinstanting that. . 2. To better...
  • Entry# 3601043
    Jul 04 2018 (12:36PM)


    @all: While we do nominally allow multiple IDs, these multiple IDs are NOT allowed to engage in misuse and "mischief". Voting multiple times in the same poll using multiple IDs, rating each other IDs' blogs using multiple IDs, etc. are classified as "gross misuse". . This is an advance notice that some of the...
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy