Hpt - ubl -vsg doubling update :
1.track laying left at A)Near munirabad 500mts
B) near Gdg station 3 kms
C) btn gdg - hulikote ..mainly 1 major bridge and 2 minor bridges
2)...
more... if swr wish they can easily open munirabad - kanaginahal and hubballi - hulikote section s within a month
3) similarly hpt - munirabad and gdg - kanaginalhal in next 3 months
4 ) finally problem lies btn gdg - hulikote section it has 3 bridges under construction which will take min 6months now just erected pillars and even swr can drag it up to one year also
5) all stations btn ubl - hpt getting 2nd pf
6) I'm not sure but few new station s may add up in hpt - ubl line ..I saw at some place they r make platform like structure
7) even Rob and Rub works are also at good speed