As per Mr dhananjay Video for Honaganahalli-Bijapur i saw sleepers are being unloaded and some are placed beside Bedding and after Bijapur i saw already sleepers laid and also tracks fixed for some patches but as we discussed deficinecy of track may delay this one but already for Bijapur-Minchanal i think they got tracks from IR now they may get for Bijapur-Jumnal strect too. But jumnal-Wandal stretch only earth works finished still sleepers not reached in this strecth may be after some month they load sleepers here too and i dont think their will be deficincy of tracks for this doubling as earlier told its In central govt NTPC PSU and also IR which both tracking this doubling and also Customer funding done so no any hurdles will come i guess..