Udaipur - Chittaurgarh Electrification Progress Report (with pics). Official target March 2019.
1. No work at all between Chittaurgarh and Chanderiya, or Chittaurgarh and Berach Jn Cabin. I haven't traveled on the Chanderiya - Berach Jn Cabin bypass, but I'm not hopeful.
1....
more... Wiring done between Berach Jn Cabin and about halfway to Ghosunda, but in a way that's somewhat loose. See pics 1 and 2.
2. Around Ghosunda, wiring becomes more of the tense sort we are used to seeing. See pics 3 and 4.
3. There is a traction substation being raised just outside Ghosunda. See pic 5.
4. The finished sort of wiring continues all the way to Kapasan. See pic 6.
5. Happily, the depot at Kapasan is almost depleted. See pics 7 and 8, which also includes a loaded wagon with Cu-Cd wires ready to be strung.
6. Between Kapasan and Bhupal Sagar, there are no wires, but wire supports have been attached. See pic 9. Stands to reason that this will be wired next.
7. Between Fatehnagar and Mavli, there are poles but no wire supports. Poles also vanish in the 500m region surrounding Mavli. See pics 10 and 11.
8. About 3 km after Mavli, poles give way to cemented foundations. See pic 12. These continue till about 2 km after Khemli, and stop totally as the terrain roughens up. However, Debari station has some cemented foundations.