up line
3) Pit for OHE pole / relay cabinet
4) Foundation for OHE pole
5) Foundation for relay cabinet
6) to 8) Foundations for OHE pole
тП║я╕ПAdjacent down line
9) Foundation for relay cabinet
10) to 12) Foundations for OHE pole
13) Foundations for relay cabinet
тП║я╕ПOHE poles adjacent both up & down lines
14) to 16) OHE poles (not aligned) were spotted after 209.0 km
17) Aligning of OHE poles under progress at 209.7 km
18) & 19) Aligned OHE poles were spotted after 209.7 km
ЁЯФ╕Update regarding ROB 267B (locally known as Satya Narayana Pet bridge) -
#SNPetROBтП║я╕ПTowards Gandhi Nagar / Nehru Colony
20) to 22) Construction of pillars completed. Girders placed on pillars for entire stretch
тП║я╕ПTowards Satya Narayana Pet (S N Pet)
23) to 26) Construction of pillars completed. Girders placed on pillars for entire stretch
27) & 28) Road construction under progress
Pictures source: Self