Ballari - kudutani -Hsapete RE update:
only OHE pit hole work completed btn BAY -KDN .poles fixing work yet to start
1.TSS coming near BYC2 ,men at work..
2. Kudutani RS almost Electrified
3&4....
more... OHE inspection car at KDN
wiring work full swing btn KDN -daroji
5.after daroji before TNGL poles with insulator
6.poles at TNGL
7. fixing poles putting concrete at TNGL.
8. RE at TNGL
9. workers picking poles..
10.last couple of poles after TNGL towards HPT
11.towards Ranjithpura line only few pit holes can be seen ..
Btn TNGL- HPT only pit hole work completed ..poles fixing work yet to start..
12.special pic: This horse At BAY Entrance welcome me again .. he looks very sick& very sad..