Oct 24 2020 (07:05) FM Approval by: Deepesh Choudhary^~/1272990
Kulali - Savalgi doubling update as on Oct 6, 2020 from RVNL CPM Mumbai :
Apparently there was an issue with a bridge in this section due to some local agitation. This issue has been resolved. Commissioning tolerances for the track is being achieved. Struggling with manpower shortages. Commissioning in Oct / Nov still appears in reach. Dates not confirmed yet. This... more...
Pophlaj Station closure has received approval from CRS. So it has been closed for starting the doubling. This news is confirmed by rvnlcpmpune and iss also present in the comments section of the above twitter post.
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.