#Pune_Miraj_Electrification
●Miraj Shenoli :- Electric Line
●Shenoli to Koregaon :-Wiring is completed and POST wiring work is going on(installing Power supply,Etc)
CRS might happen in next 1-2 months
●Koregaon to Satara :- Brackets are...
more... installed
●Satara to Jarandeshwar:- Wiring work in progress from Satara outer(2-3 kms from STR)
●Jarandeshwar to Wathar Outer(1 kms before Wathar) :- Wiring work is 90% Completed)
○Poles erected and bracketing work done at Wathar PF1 no Poles on Mainline and other Loop line
●Wathar to Adarki outer(1 km before adarki):-brackets installed Wiring work to start soon
●Adarki Outer to Lonand Wiring Work almost done
●Lonand To Valha Wiring Work 90% done
●Valha to Daundaj Wiring work on 2nd line is in progress
●Daundaj to Jejuri Wiring work 95% Done
●Jejuri to Pune Line is Electricfied
So,Miraj Pune can be Electricfied by December 2021