Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 Followed
 Rating
 Correct
 Wrong
 Stamp
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
News Super Search
 ↓ 
×
Member:
Posting Date From:
Posting Date To:
Category:
Zone:
Language:
IR Press Release:

Search
  Go  

रेलफैनों की तो बात ही कुछ और है

Full Site Search
  Full Site Search  
 
Tue Aug 4 10:59:13 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Topics
Gallery
News
FAQ
Trips/Spottings
Login
Feedback
Advanced Search
<<prev entry    next entry>>
News Entry# 414205
Jul 15 (09:10) Bullet Train Project Acquires 60% Land but Unlikely to Meet 2023 Deadline (m-thewire-in.cdn.ampproject.org)
0 Followers
5782 views

News Entry# 414205  Blog Entry# 4669313   
  Past Edits
This is a new feature showing past edits to this News Post.
New Delhi: Despite facing public protests and resistance from the Maharashtra government, the country’s first bullet train project between Ahmedabad and Mumbai has been able to acquire almost 60% of the land required for the project. However, meeting the December 2023 deadline is still a cause of concern for Prime Minister Narendra Modi’s pet project on the back of the COVID-19 outbreak.


...
more...

“We are on a fast track. We have acquired 60% of the land required for the project. Interestingly, in Gujarat it goes up to around 77%,” said Achal Khare, managing director of the National High-Speed Rail Corporation (NHSRCL), the company in charge of India’s bullet train road map.

The total land requirement for the Mumbai-Ahmedabad high-speed rail corridor project was reduced to 1,380.08 hectares (ha), from 1,434.47 ha late last year, mainly due to the actual reconciliation of the project scope. Of the total land required, 1,004.91 ha is private land. So far, around 820-830 ha has been acquired by NHSRCL.



The government has signed a loan agreement with the Japan International Cooperation Agency (JICA) for providing Rs 15,000 crore out of the total loan amount of Rs 88,000 crore. The estimated total cost of the Mumbai-Ahmedabad project is Rs 1.08 trillion, of which 81% of the cost would be funded through the loan from JICA.

Despite strong opposition from Maharashtra chief minister Uddhav Thackeray, the project is on track,  “If someone gives a loan without interest or loan with minimal interest, that does not mean we take it and snatch land from farmers. This is a white elephant,” Thackeray said in an interview to Marathi daily Saamana.



“A large chunk of land acquisition is complete. Ironically, people’s queries are not answered in social impact and environment impact hearings. The land is being acquired forcefully in Gujarat. Even in Maharashtra, the government has changed the rules from the earlier model of direct purchase. However, acquiring land in areas like Palghar in Maharashtra and Navsari in Gujarat might be a difficult task for the authorities,” said Krishnakant Chauhan, an office-bearer of the National Alliance of People’s Movements.

Apart from land acquisition, another major cause of concern before the project is the escalation of the cost due to the fall in rupee against the Japanese yen. Moreover, farmers in Maharashtra were asking for a higher compensation package.

The 508.17-kilometre long network will pass through three districts (Mumbai, Thane, and Palghar) in Maharashtra and eight districts (Valsad, Navsari, Surat, Bharuch, Vadodara, Anand, Kheda and Ahmedabad) in Gujarat.

The alignment also passes through a small section in the Union Territory of Dadra and Nagar Haveli. Though the state government of Maharashtra was showing discontent, it had recently amended state land rules to start the process of acquisition as direct purchase of land was taking too much of time.

Last year, the company had floated nine civil work tenders, which Khare said would be opened by the end of July or early August. One of the civil work contracts for the construction of stations, bridges, viaducts, maintenance depots and tunnels across the network is to the tune of Rs 20,000 crore. However, key tenders, including Shinkansen technology like electrical, rolling stocks, signalling and tracks will be open to only Japanese companies.

By arrangement with Business Standard.
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy