Jan 15 (09:04) Kochi Railway Stations' Renovation Progressing on Schedule
Entry# 6420193   
  Past Edits
Jan 15 2025 (09:04)
Station Tag: Ernakulam Town (North)/ERN added by karbang~/50057

Jan 15 2025 (09:04)
Station Tag: Ernakulam Junction (South)/ERS added by karbang~/50057
Development work at Ernakulam Junction, Town stations on schedule, says Railways

The Ernakulam Junction and Town railway stations in Kochi are undergoing renovations with a 36-month deadline. Junction station (Rs 299.95 crore budget) is nearing completion of pile foundation and column work for the east terminal building. The MLCP foundation is complete, with ground floor structural work underway. Office building structural...
more...
work is finished, with finishing touches in progress. Town station (Rs 150.28 crore budget) is progressing with second-floor work on the west terminal building and ground floor block masonry. Segment I is to be commissioned soon. The Town station's MLCP second floor is under construction (target completion 2026). Residential tower units are structurally complete (plastering in progress). The foot overbridge foundation is complete, with fabrication underway in two phases. Junction station additions include multi-storey buildings (62,000 sqm), a three-storey terminal, booking facility, hospital, 14 escalators, 22 lifts, and an MLCP with EV charging. Annual footfall: Junction - 1.96 crore+, Town - 1.02 crore+.

Kochi ke Ernakulam Junction aur Town railway stations pe 36 mahine ke deadline ke saath renovation ka kaam chal raha hai. Junction station (299.95 crore ka budget) mein pile foundation aur east terminal building ke liye column ka kaam khatm hone wala hai. MLCP ki foundation complete hai, ground floor ka...
more...
structural work chal raha hai. Office building ka structural work khatm ho gaya hai, finishing touches chal rahi hai. Town station (150.28 crore ka budget) mein west terminal building ki second floor ka kaam aur ground floor ka block masonry chal raha hai. Segment I jaldi commission hone wala hai. Town station ka MLCP second floor ka construction chal raha hai (2026 target). Residential tower units structurally complete hai (plastering chal raha hai). Foot overbridge ki foundation complete hai, fabrication do phases mein chal raha hai. Junction station mein multi-storey buildings (62,000 sqm), teen floor ka terminal, booking facility, hospital, 14 escalators, 22 lifts, aur EV charging wali MLCP ban rahi hai. Annual footfall: Junction - 1.96 crore se zyada, Town - 1.02 crore se zyada.
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy