Project Name: Commissioning of 6th Line Between Goregaon and Kandivali Stations
Length: Approx. 4.5 km
Duration: 42 days (35 working days)
Start Date: Night of August 27/28, 2024
Project...
more... Overview:
· The 6th line will be laid east of the existing tracks from Goregaon to Malad (S) and from Malad (N) to Kandivali.
· At Malad station (MDD), due to space constraints, the 6th line will be laid on the west side, necessitating the shift of all five existing lines to the west through cut and connection.
All 5 cut connection blocks will operate on weekends on Saturday/Sunday.
Mega Block Schedule:
1. First Mega Block:
· Date: 31/01-09-2024
· Duration: 10 hours
· Impact: 150 suburban cancellations, 60 short terminations, 50-60 delays.
2. Second Mega Block:
· Date: 07/08-09-2024
· Duration: 10 hours
· Impact: 150 suburban cancellations, 60 short terminations, 50-60 delays
There will be no work from 11.09.2024 to 17.09.2024 due to Ganpati Festival.
3. Third Mega Block:
· Date: 21/22-09-2024
· Duration: 10 hours
· Impact: 180 suburban cancellations, 60 short terminations, 50-60 delays
4. Fourth Mega Block:
· Date: 28/29-09-2024
· Duration: 10 hours
· Impact: 200 suburban cancellations, 60 short terminations, 70 delays
NI work at GMN will Start from 29/30-09-2024 During GMN NI (for 5 Days)
· Impact: 90-95 Avg suburban cancellations, 70-75 avg short terminations, 110-120 avg delays.
5. Fifth Mega Block:
· Date: 05/06-10-2024
· Duration: 10 hours
· Impact: 100 suburban cancellations, 30 short terminations, 60-70 delays
Due to caution order on all lines, daily 20-22 long distance trains will be regulated by 15-20 minutes.
Along with this, from 28/29-09-2024, non-interlocking work will also be done on 5th line between Goregaon and Kandivali.
Due to this, trains running from Bandra Terminus will be regulated by 40-45 minutes.
Benefits:
· Decongestion of the 5th line between Goregaon and Borivali.
· Improved punctuality for trains originating and terminating at BDTS.
· Enhanced suburban train punctuality.
· Creation of additional train paths.
Source- DRM BCT X handle
please wait...Translate to HindiProject Naam: Goregaon aur Kandivali Stations ke beech 6th Line ka Commissioning
Lambai: Lagbhag 4.5 km
Duration: 42 din (35 working days)
Shuruwaat ki Tarikh: 27/28 August, 2024 ki raat
Project Overview:
· 6th line, Goregaon se Malad (S) aur Malad (N) se Kandivali tak, existing tracks ke east mein dali jayegi.
· Malad station (MDD) mein, jagah ki kami ki wajah se, 6th line west side mein dali jayegi, jiske liye saare paanch existing lines ko cut aur connection ke through west mein shift karna padega.
Saare 5 cut connection blocks, weekend pe, Saturday/Sunday ko chalege.
Mega Block Schedule:
1. Pehla Mega Block:
· Tarikh: 31/08-09-2024
· Duration: 10 ghante
· Impact: 150 suburban cancellations, 60 short terminations, 50-60 delays.
2. Dusra Mega Block:
· Tarikh: 07/08-09-2024
· Duration: 10 ghante
· Impact: 150 suburban cancellations, 60 short terminations, 50-60 delays
11.09.2024 se 17.09.2024 tak Ganpati Festival ki wajah se koi kaam nahi hoga.
3. Teesra Mega Block:
· Tarikh: 21/22-09-2024
· Duration: 10 ghante
· Impact: 180 suburban cancellations, 60 short terminations, 50-60 delays
4. Chautha Mega Block:
· Tarikh: 28/29-09-2024
· Duration: 10 ghante
· Impact: 200 suburban cancellations, 60 short terminations, 70 delays
GMN mein NI ka kaam 29/30-09-2024 se shuru hoga GMN NI ke doran (5 din ke liye)
· Impact: 90-95 avg suburban cancellations, 70-75 avg short terminations, 110-120 avg delays.
5. Paanchva Mega Block:
· Tarikh: 05/06-10-2024
· Duration: 10 ghante
· Impact: 100 suburban cancellations, 30 short terminations, 60-70 delays
Saare lines pe caution order ki wajah se, rozana 20-22 long distance trains 15-20 minutes regulate honge.
Iske saath hi, 28/29-09-2024 se, Goregaon aur Kandivali ke beech 5th line pe non-interlocking ka kaam bhi hoga.
Is wajah se, Bandra Terminus se chalne wali trains 40-45 minutes regulate hongi.
Fayde:
· Goregaon aur Borivali ke beech 5th line ka decongestion.
· BDTS se originate aur terminate hone wali trains ki punctuality mein sudhar.
· Suburban train punctuality mein sudhar.
· Additional train paths ka nirman.
Source- DRM BCT X handle