99.9% electrification work done between rok nrw including wiring at all stations en route except jind &nrw
in jind only wiring is left and in nrw almost everything is left.
between nrw and jhl work is going on both electrification and changing of semaphores +block cabin interlocking with PI. that's why it is taking more time.
MACLs poles are erected on all the stations...
more... between nrw-jhl(not sure about TUN)
Poles are erected till maisar khana (tohana - bathinda)