MUNIRABAD-RAICHUR( GINIGERA-GANGAVATHI=45KM) NEW LINE 165KM UPDATE:
1.TRACK COMPLETED FROM GINIGERA TO CHIKKABENKAL STATION=27KM
2.FROM CHIKKABENKAL TO GANGAVATHI GROUND LEVELING COMPLETED BUT YET TO PLACE SLEEPER BEDS=13KM
3.FROM GANGAVATHI TO TOWARDS RAICHUR GROUND LEVEL WORK GOING ON ABOUT 4KM
4....
more... BUDHAGUMPA STATION, JABBALGUDDA STATION & CHIKKABENKAL STATION WORK WILL BE COMPLETED BY THIS YEAR END
5. GANGAVATHI STATION WORK JUST NOW BEGAN HOPEFULLY COMPLETE IN ONE YEAR
TOTAL 165KM = 27KM COMPLETED +17KM UNDER CONSTRUCTION + REMAINING STILL UNDER LAND Acquisition.