Tumkur-Arsikere Doubling Updates (Latest)
- Tumkur-Nittur (27km) & Banasandra-Arsikere (47km) section doubling work is completed & commissioned for traffic
- Pending work is between Nittur-Banasandra (22km)
...
more... - a) Nittur-Sampige Road (11kms) track work is completed (Only station yard linking is pending)
b) Sampige Road to Ammasandra track work yet to be started in many locations
c) In Ammasandra village Land acquisition is pending near Heidelberg Cement Factory
d) Ammasandra-Banasadra track work is going at very slow pace
Here is the video update: