Update of NI work Adra.
Day 1 - Dismantling of old X-over No.105A&105B with linking of X-over 132A&132B(Adra-Joc up&DN line),connection of Joc-Adra DN line with point No.126A & also connection of X-over point No. 133A-133B have been done on 27.5.22 during 1stday of NIwork of Adra which improve Train operation.
Day...
more... 2- Dismantling of existing X-over 107A with linking X-over No. 127A and 127B after insertion of T/out No.127A has been done on 2nd day of NI work of Adra yard on 28.5.22 for improvement of smooth train operation.
Day 3 - On 29.5.22, 3rd Day of NI work at Adra yard , Dimond Crossing 104A & 103B have been dismantled and linking with new Point no 123 at same location. 1 out of 6 Dimond Crossing has been dismantled on this day.