Admins,
The following are a few updates regarding BZA & GNT divisions.
GNT:
1. The Guntur- Tenali stretch is undergoing doubling and electrification of the present single electrified line.
2. The Guntur - Guntakal stretch...
more... is undergoing electrification of single line and electric poles have reached past KM 200 & a little beyond Giddalur starting from GNT.
BZA:
1. The doubling and electrification works are in progress from Vijayawada to Bhimavaram. Work started in 2013. But, as of electrification, OHE poles haven't come up yet for most of the stretch.
2. Works on Gudiwada - Machilipatnam. Bhimavaram- Nidadavolu, Bhimavaram- Narsapur stretches are yet to start.
Please make a note of this and make necessary changes in the Atlas.
If you want pictures regarding the same I'll give u those that I have.
Thank you in advance.
#Moderator.