Now countdown is started for the engine trial which will be done on SOY-Ghansore new BG section as BG work on SOY-Ghansore section is nearing completion and SECR already ordered thier ofcls to complete the remaining work within 10 days and after that engine trial will be done on SOY-Ghansore section and CRS will be invited for inspection and as per now Ghansore-NIR section work is going on and it is possibly complete in March end so after that only in Apr 2017 Ghansore -NIR section will be open...
more... for traffic after green signal from CRS and as per SECR existing JBP-SOY passenger will be extended to Ghansore once CRS green signal and by Apr 2017 again it will be extended till NIR and work of NIR-BTC is also going on at good pace and it can be completed by next year March so hope by Next year this time full section JBP-NIR-BTC will be ready for train operations if all works will be done on time