Please comment on these new rail lines -
For a new railway line project to be profitable its Rate of Return (ROR) should be at least 14%.
Now see ROR of these new rail lines in NER (All are in minus)-
1. Basti-Kapilvastu ------------- 91 kms -1.16%
2....
more... Ghughli-Anand Nagar ------47 kms -1.40%
3. Khalilabad-Bahraich -------240 kms -1.92%
4. Sahjanwa-Dohrighat -------82 kms -1.86%