Updates on electrification work of PPI-JBP section as on 28/05/2017.
1. From PPI to GARD the work of digging hole is completed.(GARD outer)
The work of digging hole is to be start on GARD station.
2. GARD-NU the hole work is completed. The work of OHE is going on KY station.
3....
more... NU-SRID the work ohe pole and wiring is also completed.
Only some part of wiring has to be tightned.
4. SRID-KEQ hole work is completed and work of OHE is done till KEQ outer.
5. KEQ-JBP the work of digging holes is completed till 2nd No.bridge (almost JBP outer). The hole work is almost completed in MML station.(the work of OHE pole will be start soon). The work of digging hole will also be start soon in JBP station.
By this pace I think PPI-JBP section will be completed in the end of the year (December). And we can se elocos in this route by January 2K18.ЁЯШМтШ║