Gwalior Sheopur GC Project update -
Bamour Gaon. (BMZ)
1.The work of laying railway track is going on fast in
Bamour Gaon.
2.The...
more... work of building a bridge on the Sank river is
almost ready.
3.NH-44 ROB base work on progress near Bamour
Gaon (BMZ) and this overbridge almost complete
but few works are incomplete.
4.The building of Bamour Gaon Railway Station is
80% complete and the platform is also 80%
complete.
5.Tracks are being laid at some places and along
with this the work of electrification is also going
on.
Pic Credit :-RF Arun Singh Rajawat
please wait...Translate to EnglishYo, listen up. Here's an update on the Gwalior Sheopur GC Project at Bamour Gaon (BMZ).
1. They're laying down the train tracks pretty dang fast at Bamour Gaon.
2. The bridge being built over the Sank river is almost ready for action.
3. They're currently working on the NH-44 ROB base near Bamour Gaon (BMZ) and the overbridge is almost complete. There's just a few little things left to do.
4. The Bamour Gaon Railway Station building is 80% finished and so is the platform.
5. They're installing tracks in certain spots and working on electrification at the same time.
Pic Credit: RF Arun Singh Rajawat (You got that?)
please wait...Translate to HindiGwalior Sheopur GC Project ki update -
Bamour Gaon (BMZ).
1. Rail ki patri dalne ki kaam tezi se chal rahi hai Bamour Gaon mein.
2. Sank nadi par phatak banane ki kaam tayyar hai.
3. Bamour Gaon (BMZ) ke paas NH-44 ROB ke base work par kaam jaari hai aur yeh overbridge shaamil hai lekin kuch kaam baaki hai.
4. Bamour Gaon Railway Station banane ki kaam 80% complete hai aur platform bhi 80% complete hai.
5. Kuch jagah track lag rahi hai aur saath hi electrification ka kaam bhi chal raha hai.
Pic Credit: - RF Arun Singh Rajawat