Kota - Bina Doubling Progress
A. Sogaria - Ruthiyai Section
1. MotiPura Chauki - Bhulon
Track is ready, OHE wires are installed
Bhulon...
more... station : Demolition of old building under process, new building is ready to serve, Civil work of PF is pending & construction of FOB is started
2. Bhulon - Chhabra Gugor
Track is ready, OHE wires are installed
Chhabra Gugor station : PF almost ready, only minor work is pending & OHE wire need to be installed at new PF
3. Chhabra Gugor - Kesholi
Just After Chabbra, LC post was removed so track laying work is pending in very little part
Further, Track is ready, OHE wires are stretched except for a part of less than 500m where only cantilevers are installed
Kesholi Station : Track laying work for new PF is under progress & PF work will take more time
4. Kesholi - Salpura
From Kesholi towards Salpura, connection of loop line to main line is missing, tracks need to be layed.
further track of 2-3km is Ready, OHE poles are erected with cantilevers
after that only track bed is ready for Andheri River bridge + three minor bridge + lahasi river Bridge
No work has been started for new PF at Salpura
B. Guna - Bina
only left section was Kanjiya - Pipraigaon, which is now ready to be inspected by CRS. loco trial has been done
C. Sogaria - Kota
this is only part which is untouched till date.
But once started it won't take much time as they could revive two old loop lines which are not used by changing their alignment. OHE poles are visible on this blank section (without track) with cantilevers installed till Kota Junction.
May be this is delayed because of wagon repair shop's yard.
Bina Mahadeokhedi - Malkhedi Doubling
This is ready to be inspected by CRS