Highlights of run (Day 7 - 18.02.24 - Sun);
1) NDLS - AGC ;
= Rescheduled by 2h 25m late at 23:30 from NDLS because of some unknown reasons, as return train 12621...
more... arrived NDLS today morning before 9am.
= All trains are very late as they approach MTJ, at 23:30, more than 8-9 trains line till MTJ including KK which left 20:30
= Finally, dep NDLS 23:33 - 2h 28m late,
- H Nizamuddin 23:50 - 2h 40m late,
- Okhla 23:54 - 2h 41m late, /51 kph
- Tuglakabad 00:02 - 2h 44m late,
- FDB New Twn 00:14 - 2h 46m late,
- Ballabhgarh 00:19 - 2h 48m late,
- Asaoti 00:28 - 2h 50m late,
- Rundhi 00:48 - 2h 55m late,
- Sholaka 01:04 - 3h 4m late,
- Kosi Kalan 01:18 - 3h 1m late, /98 kph
= Arrived AGC 04:08 - 4h 43m late, did NDLS AGC in 4h 43m late,
------------------------------------------------------------------------------
2) AGC - GWL - VGLJ ;
= AGC GWL in 1h 27m,
= Stats after GWL 05:42 - 4h 27m late,
- Karari 06:56 - 4h 30m late,
= Reached VGLJ 07:15 - 4h 38m late, did GWL VGLJ in 1h 33m.
------------------------------------------------------------------------------
3) VGLJ - BPL ;
= Stats after VGLJ 07:21 - 4h 38m late,
- Khajraha 07:44 - 4h 46m late, 45 kph
- Burhpura 07:50 - 4h 41m late, 64 kph/130 kph
- Dailwara 08:17 - 4h 28m late, 86 kph
- Agasod 09:11 - 4h 28m late,
- Bina Jn. 09:36 - 4h 46m late,
- M Bamora 09:51 - 4h 47m late,
- Salamatpur 10:51 - 4h 37m late,
- Bhdbdaghat 11:00 - 4h 30m late, /121 kph
- Suksweniyan 11:04 - 4h 28m late, /113 kph
= Arrived BPL 11:15 - 4h 30m late, did VGLJ BPL in 3h 54m.
= Trailed 11058 ASR CSMT from Dhaura to Bina, which led to TN overtake 11271 Vindhyachal at Bina. NCR did not allow the overtake, but when it entered WCR, 11058 overtake happened at Mandi Bamora.
------------------------------------------------------------------------------
4) BPL - ET ;
= Stats after BPL 11:27 - 4h 37m late,
- Habibganj 11:41 - 4h 44m late,
- Mandideep 11:52 - 4h 36m late,
- Barkhera 12:08 - 4h 24m late, Ghat starts
- Midghat 12:23 - 4h 25m late,
- Budni 12:29 - 4h 23m late, Ghat ends
- Nrmdprm 12:34 - 4h 20m late,
- Pwrkheda 12:42 - 4h 17m late,
= 12296 Sangha approaching ET from JBP, if it leaves ET first , TN will have to go behind Sangha till GDR, as it is running with 1hr+ delay which is much less than TN. Let's see.
= 12296 ET (11:50/13:00) it was way ahead, when TN approached ET , Powarkheda at 12:42.
= TN arrived ET @ 13:08 - 4h 33m late,
------------------------------------------------------------------------------
5) ET - NGP ;
= Stats after ET 13:33 - 4h 53m late, 25m halt
- Kiratgarh 13:46 - 4h 57m late,
- Kesla 13:49 - 4h 54m late, /114 kph
- Pola Patthar 14:01 - 4h 46m late, /117 kph
- Dhodra Mohar 14:06 - 4h 44m late,
- Ghoradongari 14:22 - 4h 41m late, 86 kph/120 kph
- Kohli 17:03 - 4h 30m late,
= Arrived NGP 17:52 - 4h 47m late, ET NGP in 4h 19m.
= Interestingly, CR allowed the overtake of Sangha, if they wanted to do so, they should have done at ET.
------------------------------------------------------------------------------
6) NGP - BPQ - WL ;
= Stats after NGP 18:13 - 5h 3m late, 22m halt
- Ajni 18:24 - 5h 11m late,
- Buti Bori 18:53 - 5h 17m late,
- Tuljapur 19:12 - 5h 11m late,
- Seloo Rd 19:17 - 5h 6m late, /119 kph
- Sewagram 19:27 - 5h 6m late,
- Sonegaon 19:38 - 5h 1m late, /92 kph
= Had 27mins halt at BPQ, did BPQ WL in 4h 17m.
------------------------------------------------------------------------------
7) WL - KMT - BZA - MAS ;
= From WL both 12296 Sangha and TN went behind 20804 GIMB VSKP SF till BZA.
= From BZA went behind Pinakini till MAS.
------------------------------------------------------------------------------
please wait...Translate to EnglishDay 7 Recap (24th Feb, Sunday):
1) NDLS to AGC:
- Got delayed by 2 hours and 25 minutes at 23:30 from NDLS due to some unknown reasons.
- All trains were running super late as they approached MTJ, with about 8-9 trains in line till MTJ.
- Finally departed NDLS at 23:33, 2 hours and 28 minutes late.
- Reached AGC at 04:08, 4 hours and 43 minutes late.
2) AGC to GWL to VGLJ:
- Reached GWL in 1 hour and 27 minutes.
- Arrived at VGLJ at 07:15, 4 hours and 38 minutes late.
3) VGLJ to BPL:
- Reached BPL at 11:15, 4 hours and 30 minutes late.
- Had some interesting moments with other trains along the way.
4) BPL to ET:
- Arrived at ET at 13:08, 4 hours and 33 minutes late.
5) ET to NGP:
- Reached NGP at 17:52, 4 hours and 47 minutes late.
6) NGP to BPQ to WL:
- Completed BPQ to WL in 4 hours and 17 minutes.
7) WL to KMT to BZA to MAS:
- Journey progressed smoothly, followed some other trains along the route.