Update as on 1/05/2017 : Rewari-Bhiwani-Hisar#Doubling#Electrifcation
#Doubling work reached to Manheru.Bllasted stone have been laid down over 80% of section between KSI-MHU while almost the same for rails.Where as 20% section in which in some part nothing happened yet or track linking left.
Second Plateform work is in progress at MHU,CKD and Jahrli station.
#Electrifcation work reached to MHU outer in which...
more... basic structure is being constructing near MHU outer.
Poles have been erected till CKD outer on both line (running line completed whereas on new line it covers almost 95%) whereas basic structure is approaching MHU.OHE mast n clips on running line till CKD and wiring has been done on both line 5 kms towards MHU to KSI
#1 - Manheru Station second PF
#2 - Jharli station second PF
#3 - Section between Kosli-Jharli
#4 - Kosli Station
#5 - Jatusana Station
#6,7,8 - Approaching Rewari where OHE is rising up to 7.5m
#9 - Bhiwani Junction and stored poles
#10 - At rewari Junction , Double stack container under High Rise OHE !
Update Given By Akash Member#1169627