On entire Pune-Daund Route of 75 Kms, wiring work is almost complete for 70 Kms or so. Only wiring of 2-3 Kms near Pune (GIT End) and another 2-3 Kms enroute is yet to be done. DD-MMR Electrification Work is complete. Only Daund Station and Yard is yet to come under wires. Initially, the plan was to make AC Traction 'live' on Pune-DD-MMR Section by 02-Oct-2015! However, recently, with some problems as well as major problem of land acquisition for TSS, the project is getting delayed. Now, we can expect AC Traction to be live surely by 02-Oct-2016! Sad and Unfortunate, however, likely to be true!