- Ringas - Phulera electrification
Rewari Ringas Complete. CRS pending
.
Ajmer - Marwar - Rani - Palanpur electrification -- Target Feb 2018
/blog/post/1763953 .
Ajmer - Udaipur Electrification 294km Target March 2019 - Cost 315 crore
Work started in August 2016 --- Ajmer Bhilwara Target March 2018
.
Jaipur Sikar gauge conversion - 107km -
.
Ajmer Palanpur 358km doubling excl Moribera- Swarupganj (48km)
-- (a)Marwar Guriya Doubling 47km
Marwar - Chandawal commissioned
Chandawal - Guriya - CRS completed.
.
--(b)Bangurgram - Guriya doubling 47km
.
--(c) Ajmer bangurgram doubling 47km ---- Target December 2018
.
--(d) Marwar Rani 52km doubling 335 crore - started in Jan 2016
.
.
--(e) Mori Bera - Jawai Bandh - Falna - Khimel - Rani 40km
Executed by
#RVNL .
.
--(f) Karjoda palanpur 9km target is feb 2017
.
--(g) Swarupganj - Bhimana - Abu Rd - Sarotra Rd - Karjoda 72km
executed by
#rvnlSwarupGanj - Bhimana 9km CRS completed on 11 March 2017
.
Dausa - deedwana - gangapur city new line ( 70% complete )
(a)Dausa - deedwana completed
(b) Deedwana gangapur city -
.
Phulera Degana doubling
EPC tender given to Punj Lloyd
.
Alwar Bandikui Doubling ( Total cost 280 crore ) -- target Oct'18
.
Ajmer Sawai Madhopur ( Nasirabad - Chauth ka Barwara ) new line ( 873 crore ) - 165km
Fls work started wef 28.3.2016
.
Mavli Barisadri Gauge conversion ( 82km) - Work started in Nov 2016
.
Marwar Mavli Gauge conversion - 1600 crore - 152km - Waiting for
#CCEA approval
.
Pushkar Merta new line - ( 323 crore ) - Waiting for
#CCEA approval
.
Ajmer-Kota (Nasirabad-Jalindri) (145 km) - ( 822 crore ) Waiting for
#CCEA approval
.
Himmatnagar - Udaipur gauge conversion 208km
.
ratlam dungarpur new line 189km
Work freezed.
.
Thaiyat Hamira - Sanu New Line 59km ( April '18 )
44% earthwork, 22% concreting, 26% minor bridge, 10% ballast supply completed
.
Phulera Ateli section of WDFC - Target Date March 2018 ....