Atlas #monitor now ROZA-SCC-BUW route is fully electrified and freight train also started running with e-loco. Please update this route as "Construction - Double-Line Electrification" for more please refer click here
This link says :
"In UP, he said the doubling of Roza-Sitapur Cantt-Burhwal broad gauge single line project has been approved at an estimated cost of Rs 1,295.42 crore with expected completion cost of Rs 1,486.46 crore with 5 per cent escalation per annum.
The...
more... length of the railway line will be 180.77 kms. The completion period of the project will be five years.
The doubling of this line between Burhwal junction and Roza junction will fulfill the demand of the increasing traffic leading to socio-economic development of the area. Besides, there will be continuous double line track available from Gorakhpur to Delhi via Sitapur Cantonment and Moradabad. Barabanki and Sitapur districts of UP would also be benefited through this project."