A.) 27km Alwar Dhigawara #doubling Update (Oct 2017)
Target date revised to 31 - 5 - 2018
1.12km track linking completed out of 27km
2. Earth work complete
3. Ballast supply complete
4....
more... 22 minor bridge complete , 10 remaining.
.
B.) Bandikui Dhigawara - No target Date
1. Earthwork complete 55%
2. 24 minor bridge complete 41 remaining.
3. 0km
#tracklinking