Quick batch of updates on the electrification progress on the Ratlam-Chanderiya stretch.
1. Mandsaur - Piplia Mandi: Barring a few small patches, concrete foundations and support loops are all done. No pillars anywhere in sight.
2. Piplia - Malhargarh: No foundation work, not even any amount of digging, but there are neat little heaps of cement and sand and crushed rock lying...
more... next to the track at what seem suspiciously like OHE pole intervals.
3. Malhargarh - Harkiakhal: No progress.
4. Harkiakhal - Nimach: No progress, but apropos of nothing there are a half dozen OHE poles lying in a pool of muddy water near the station.
If I see anything between Nimach and Chittorgarh, I'll post an update. I *do* have doubling related updates, which I'll post in another thread. Meanwhile, if anyone has updates on the MDS-RTM stretch, please let me know.