OHE work was going on in goods section and yard at Ballari Junction
🔸Ballari Junction outer (towards Chikjajur side)
3) to 8) Wiring started for OHE poles from 0.7 km to 1.2 km
🔸Ballari by-pass line
⏺️Hosapete end
9) Deviating point of Hosapete line and by-pass line
10) Mast erection yet to be completed for a OHE portal
11) Wiring started for 3 OHE portals
12) Wiring observed for all 3 lines viz., 2 main lines from Hosapete side and 1 by-pass line
13) Wiring for by-pass line stopped after few meters
⏺️Chikjajur end
14) No OHE poles or foundations were observed towards Chikjajur side
Pictures source: Self