#PuneSolapurGulbargaDoubling
Due to pending issue of LC gate at KWV, RB has rejected request of block for interlocking purpose.
As per railway, they can't proceed with doubling work unless LC gate at KWV is closed and removed.
But the localites are opposed this and raised issue in High Court.
Now...
more... railway is ready to construct RUB by removing LC, but railway demanding Kurduwadi Corporation to deposit 5 crs for this.
So due to this fight between railway and local government, doubling work is completely stopped even though Wadshinge to Bhalawani track is doubled and only interlocking work is remaining.