As per 6 months back Google maps we can see their is ballast put on along the bed on small groups with some distance especially near the NTPC and after Basavan Bagewadi plant but still it have lot of works to do between Minchinal-wandal=71 km so they might be divided it as 32+39 so first target is Minchinal-Jumanal=32km and later after successful commision of that they go for commissionin of Jumnal-wandal=39km but mean while hope both targetted sections works going on together... We can see the update if Mr dhananjay done video after wandal upto Bijapur.