#Doubling Update Katni-Singrauli- Chopan-Renukut- Garhwa Road and Shaktinagar Branch line
Katni-Singrauli - 261 KM ( 32 KM pending between Joba to dubri kalan) , Delayed due to Sanjay Tiger reserve. FLS completed for alternate alignment between Joba and dubri kalan to avoid tiger reserve totally. Due to this kanchanpur road station will be abandoned.
...
more...
Singrauli- Chopan - 63 KM (6 KM pending Phaprakund to Obra dam ) , delayed due to Rihand bridge construction at Obra dam. Bridge to be finished by December 2024
Chopan (BXLL ) to Garhwa Road - 141 KM. Completed
Karaila Road - Shaktinagar 32 KM ( 5 KM Anpara Road to Krishnashilla ) , pending due to curved rail bridge at Anpara.
Total including Shaktinagar branch line - 497 KM , and excluding sktn line 465 .
Doubling done 427 KM i.e. almost 91.82% .
Doubling done including sktn line 454 ie 91.34%
Completion by Zone
ECR 95.33%
WCR 87.73 %
But no trains have been introduced for passenger movement. Also alternate alignment will take minimum 2-3 years to complete.