Blog Entry# 2367525  
Posted: Jul 31 2017 (21:44)

4 Responses
Last Response: Aug 01 2017 (17:00)
  
Rail News
0 Followers
1004 views
New Facilities/TechnologyNR/Northern  -  
Jul 31 2017 (20:20)   मिशन विद्युतीकरण के जरिए डीजल को अलविदा कहेगा रेलवे

☆गोंडा इलेक्ट्रिक शेङ ■☆*^~   6751 news posts
Entry# 2367525   News Entry# 310198         Tags   Past Edits
ट्रेन से पावर कार हटाकर एक एक्सट्रा कोच भी जोड़ा जा सकेगा
नई दिल्ली
इंडियन रेलवे अब मिशन विद्युतीकरण शुरू करने जा रहा है। रेलवे का टारगेट है कि ट्रेनें चलाने के लिए डीजल पर निर्भरता को कम करके बिजली का अधिकतम उपयोग शुरू किया जाए। इसी मकसद से अब रेलवे ने थ्री फेज वाले इंजनों का उपयोग शुरू किया है, जिससे ब्रेक लगने पर बिजली रिजेनरेट होती है। इसके अलावा रेलवे ने यह भी तय किया है कि अगले 5 साल में रेलवे 25 हजार किमी की रेल लाइनों का विद्युतीकरण
...
more...
करेगा। इस तरह से अगले पांच साल में रेलवे की विद्युतीकरण वाली लाइनों का आंकड़ा डबल हो जाएगा। रेलवे मान रहा है कि अगले एक दशक में उसके इन कदमों से 26 हजार करोड़ रुपये की बचत होगी।
रेलवे के अधिकारियों का कहना है कि मिशन विद्युतीकरण इसी सप्ताह लांच किया जा सकता है। इस मिशन का टारगेट यही है कि डीजल पर निर्भरता को कम किया जाए। उनका कहना है कि एक तो डीजल के आयात से विदेशी मुद्रा खर्च करनी पड़ती है जबकि इस वक्त देश में बिजली सरप्लस है। इसके अलावा बिजली का उपयोग बढ़ाने से प्रदूषण को भी कम किया जा सकेगा।
रेलवे अधिकारियों के मुताबिक रेलवे अपने इंजनों की तकनीक को भी बदल रहा है और इसमें थ्री फेज तकनीक का उपयोग करना शुरू किया गया है। इसका फायदा यह है कि जब भी ट्रेन में ब्रेक लगता है तो उससे भी उर्जा उत्पन्न होकर वापस लाइनों में चली जाती है, जिसका अन्य ट्रेनों को चलाने में उपयोग किया जा सकता है। इस वक्त रेलवे के पास 5400 बिजली के इंजन हैं, उनमें से एक हजार थ्री फेज वाले हैं। रेलवे का यह भी कहना है कि अब तक रेलवे की ब्रॉडगेज लाइनों में से 25 हजार किमी लाइनों का ही विद्युतीकरण किया जा सका हे लेकिन अब रेलवे ने तय किया है कि अगले पांच साल में 25 हजार किमी लाइनों का और विद्युतीकरण पूरा किया जाए। इस तरह से 58 हजार किमी की ब्रॉडगेज लाइनों में से 50 हजार किमी लाइनें विद्युतीकरण वाली होंगी यानी वहां बिजली के इंजनों से ट्रेनें चलायी जा सकेंगी। थ्री फेज इंजन के इस्तेमाल से सिर्फ ब्रेकों की वजह से उर्जा उत्पन्न होने से रेलवे को 300 मेगावाट बिजली की बचत होगी।
एक्सट्रा काेच का भी फायदा
रेलवे के इलैक्ट्रिकल डिपार्टमेंट के अधिकारियों का कहना है कि इस वक्त 13 जोड़ी ऐसी शताब्दी ट्रेनें हैं, जहां अभी पावर कार तो लगी है लेकिन उसमें डीजल का उपयोग नहीं किया जा रहा बल्कि ट्रेन के अंदर एसी चलाने से लेकर हर तरह के उपकरण बिजली से ही चलाए जा रहे हैं। इससे पहले पावर कार डीजल से चल रही थी और उसी से सभी उपकरण चलाए जाते थे। शुरुआती दौर में पूरी तरह से पावर कार को नहीं हटाया गया है ताकि आपातस्थिति में उसका इस्तेमाल हो लेकिन जब सिस्टम पूरी तरह से काम करने लगेगा तो ये पावर कार हटा दी जाएंगी। इस तरह से पावर कार हटने से एक अतिरिक्त कोच भी ट्रेनों में लगाया जा सकेगा।

  
917 views
Jul 31 2017 (21:44)
a2z~   2045 blog posts
Re# 2367525-1            Tags   Past Edits
Aisee baat hai to DLW ke hote hue, Marhowra (Bihar) mein ek naya Diesel loco factory kyon khulwa rahee hai?

  
914 views
Aug 01 2017 (08:53)
☆गोंडा इलेक्ट्रिक शेङ ■☆*^~   14974 blog posts   3076 correct pred (65% accurate)
Re# 2367525-2            Tags   Past Edits
Abhi bhi kafi section diesel loco par h....kahna asan h karna mushkil bhaut tym lagega....dusra dlw bsb par kafi load h foreign countries ke demand ka isiliye dusri ban rahi....baad may upgrade kar denge koi issue nhi jaise dlw bsb may ab eloco bn rah

  
1134 views
Aug 01 2017 (09:19)
shiv2350   370 blog posts
Re# 2367525-3            Tags   Past Edits
Electrification pehle forest areas aur hilly areas mein karna chahiye jaha train pahuch chuki hai taaki ecology aur nature ko diesel ke pollution se bachaya jaa sake. After that other areas should be given priority.

  
724 views
Aug 01 2017 (17:00)
a2z~   2045 blog posts
Re# 2367525-4            Tags   Past Edits
* Over 30000 RKMs out of total 58000 BG RKMs of IR are already electrified by 31.3.17. Rate of electrification had been accelerated from 500km/yr (some years ago) to 1000km/yr (a few years ago) to 2500km/yr (2016-17)and accelerated targets of 2017-18 4000km, 2018-19 onwards 6000km/yr are set in order to electrify all BG routes in next 5 years. It can be assumed that if not in 5 years, electrification can be done in 7-8 years.
*Requirement of Dlocos have started falling and currently many trains on electrified routes are being hauled by Dlocos (due to shortage of Elocos). A large number of D-locos shall be rendered useless or shall be running on electrified routes (due to shortage of E-locos) within a couple
...
more...
of years.
* Initial plan of IR was to go for electric traction in E-DFC and for Diesel traction for double stack container operation in W-DFC. But due to Japanese interference, soon high mast electric traction for double stack container operation had to be finalised for W-DFC. IR should have cancelled the plan of new D-loco factory or should have converted it into E-loco factory at that moment itself. But surprisingly that did not happen.
* Export of Dlocos is normally of the order of 20 locos/yr, DLW is more than sufficient to handle it and produce some D-locos in future for IR, if required.

ARP (Advanced Reservation Period) Calculator

Reservations Open Today @ 8am for:
Trains with ARP 10 Dep on: Fri Oct 6
Trains with ARP 15 Dep on: Wed Oct 11
Trains with ARP 30 Dep on: Thu Oct 26
Trains with ARP 120 Dep on: Wed Jan 24

  
  

Rail News

New Trains

Site Announcements

  • Entry# 2418661
    Yesterday (07:09AM)


    @all: There are some changes coming to the PNR Forum. 1. All PNRs will be anonymized, i.e. you won't see who posted the PNRs or search PNRs by Traveller. This is to better protect the confidentiality of travelling members and their travel plans. However, members will still be able to search their OWN...
  • Entry# 2409730
    Sep 15 (11:46PM)


    In recent times, the number of FM Complaints regarding "targeting me", "offensive content", "sarcastic comment" have been increasing. This has led to increased censorship and throttling of open discussions. . This is a clarification that this site is meant for a FREE EXCHANGE of ideas. Some arguments/debates/disagreements/jokes/sarcasm are ALLOWED and are an integral...
  • Entry# 2390218
    Aug 25 2017 (12:59PM)


    There has been a partial rollout of a modification to Timeline entries. The implementation will be complete within a week. 1. Void & RAC buttons have been removed. . 2. TL Entries can now be Edited and Fixed by the original updater, if there are errors. So there is no need to Void TLs...
  • Entry# 2175399
    Feb 23 2017 (01:22PM)


    There has recently been a lot of frustration among RFs when their Station Pics, Loco Pics, Train Pics get rejected because the "number is not showing", "shed is not visible", the loco/train is at a distance, Train Board is too small, "better pic available", etc. . To address this issue, effective tomorrow, ALL...
  • Entry# 2165159
    Feb 15 2017 (09:53AM)


    A minor update, but may impact many members: Hereafter, FMs will be able to delete invalid Red Flags on Imaginary trains. Red Flags can be removed by FMs, only against specific complaints filed against the blog. This does not give all members the right to complain against EVERY single red flag they...
  • Entry# 2155798
    Feb 08 2017 (11:40AM)


    -@all members: As of recently, there has been a trend whereby minor name updates of Trains/Stations - whether such and such regional name should be there or not, whether the train should be called "Abc Express" or "Abc Superfast Express", etc. are threatening to take over the majority of Timeline entries. Also,...
Scroll to Top
Scroll to Bottom


Go to Mobile site
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.