Penukonda-Yelahanka Doubling Updates:
⏺️Penukonda-Devarpalle land levelling is fully completed
⏺️Gauribidanur Station works still pending
⏺️Dodballapur-Rajankunte (11kms) track laying & ballast work is in final stage (almost 90% of work is completed)
🔸Pending...
more... works:
⏺️LC works to be started soon
⏺️Electrification: poles can be seen in only few places
⏺️Dodballapur (Hindupur side) doesn't require much work for Doubling, but towards Yelahanka few works need to be done due to Ultra Tech cement Factory siding line