#PuneSolapurGulbargaDoubling
As per RVNL recent update, Kulali to Sawalagi doubling is in final stage and will be commissioned within 3 months. So by the month of October, Solapur - Gulbarga (Kalburgi) entire section will be doubled.
Another progress update is from Daund - Solapur section. New platform is constructed at Jeur, also underpass work is completed. Next Target is Balwani - Jeur - Pophlaj section. Land leveling is completed and track laying is in progress. Tentative completion date is Dec 2020. And for remaining section of Pophlaj - Bhigwan, waiting for...
more... official updates.
Electrification work is almost completed between Bhigwan and Kurduwadi (minor work remaining) and Kurduwadi to Miraj.